 |
 |
 |
 |
 |
 |
 |
|
|

Original artwork Howard Nourse
|
|
"Updates"
Archive Page 2
11/00-10/01
Update Archives page
1, page 2, page
3, page 4, page 5,
page 6, page 7, page
8, page 9
Please note that most of the
photos have been removed from this page to make room on the server for
more recent pictures
|
|
|
All
photos open in new window. Close new window to return to this page. |
|
|
11/09/00-
The pictures below were taken on November 9th by John
Smatlak, and show the tremendous progress that has taken place over the
last few months.
- Click on any of the images for a larger view - |
|
|
The World Cruise Center station
takes shape |
On the platform at the
World Cruise
Center station, looking
south |
|
|
|
Looking north from First St. at newly installed line
poles. |
Passing siding being installed at 5th Street, Maritime
Museum in background. |
|
|
|
|
5th street Station site |
Line
poles being installed north of
Ports
O' Call |
|
|
|
|
11/16/00- The photographs below were taken in Seattle on November
15th and in San Pedro on November 16th by John Smatlak.
As you can see from the photos, construction of the trolley infrastructure
is now progressing rapidly.
- click on image for larger view - |
|
|
|
|
Replica cars |
Replica car one |
|
|
|
|
Welders at work on steel subframe of replica car two |
Interior of replica car one |
|
|
|
|
Painters get to work on the World Cruise Center
station |
22nd St. station, line poles in place,
concrete formwork
underway |
|
|
|
|
Two views at 5th St., looking north, showing installation of bracket
arms. Note newly installed passing siding in foreground. |
|
|
|
|
|
12/22/00
Latest construction and car updates
As December draws to a close, the trolley
infrastructure is approaching completion. All of the track work has been
completed, more than half of the overhead wire has been strung, the
substation has been delivered and installed, and work is now underway on
all four stations. Car 1058 is having its electrical and airbrake
equipment installed, and work on replica cars 500 and 501 is proceeding
rapidly.
-John Smatlak photos,
click on any image to enlarge- |
|
|
|
|
Station at 6th Street |
Aerial view at 6th St. |
|
|
|
|
Prototype platform ramp, shown being
raised to "up" position. |
Prototype
platform ramp,
shown
in down position. |
|
|
|
|
22nd St. station site, substation
installation underway |
Control
system wiring being
installed
on car 1058 |
|
|
|
|
Woodwork being installed on replica
car 500- 12/20/00 |
Crews
at work discussing electrical
layout
underneath car 500 |
|
|
|
|
1/16/01
Construction Updates
As of the middle of January, the traction power
system is in the final construction stages, with the substation now
installed at 22nd Street along with the new DWP equipment for incoming
power. The new crossing signal equipment has been installed at 5th and 6th
Streets, and curb work is about to commence to permit installation of the
new equipment at 1st Street. Stations one and two both have their wooden
shelters installed and painted, work on the shelter at station four is
underway, and crews are preparing to pour the concrete platform at station
three adjacent to Ports O' Call.
-John Smatlak photos,
click on any image to enlarge- |
|
|
|
Line crew at work in January. Ports
O' Call station under construction in background. |
Station
at 6th St., new passing
siding
visible in background |
|
|
|
|
Construction
at 22nd St.
Substation
in foreground. |
World
Cruise Center station
nears
completion, January 2001. |
|
|
|
|
3/4/01
Project Updates
As of the beginning of March, the traction power
system has been installed, with work continuing on alignment. Station One is complete except for the platform ramps. Stations
Two and Four are essentially complete except for their railings and the
platform ramps. At Station Three, the concrete work is complete, and
construction of the waiting shelter is underway.
In San Pedro, good progress is being made on
conversion of car 1058 back to rail operation. All of the Goodman control
system components have been installed, the low voltage wiring has all been
run, new window glass has been installed where needed, the ceiling has
been painted, and installation of equipment in both cabs is nearing
completion. Also, both trucks have been reassembled with their refurbished
traction motors and new wheels, and work has begun on installing the
truck-mounted brake cylinders. Finally, installation of air brake
components and piping underneath the car has also begun.
Work on the two replica cars in
Seattle is also progressing rapidly. As can be seen in the photos below,
the first car is really taking shape. Almost all of the exterior woodwork
has been installed, along with the framing for the interior woodwork. Most of
the underbody components have been installed, and the extensive truck
rebuild process has been completed on the first pair of trucks.
Fabrication of seats and other interior components is also well along. Car
number two is following about 30 days behind the first car.
-
John
Smatlak Photos -
-
click
on any image to enlarge -
|
|
|
|
|
|
Station Three- February |
World Cruise Center Station |
|
|
|
|
|
|
|
Shop
scene 2/20/01 |
World
Cruise Center Station |
|
|
|
|
Shop scene 2/20/01 |
|
|
|
|
|
|
|
5/22/01
Project Updates
PE 1058- Contractor F&M Locomotive is
closing in on completing the initial phase of conversion work on car 1058 in San Pedro.
A
substantial amount of work has taken place on the car since our last
update. Highlights include: the majority of the airbrake apparatus and
piping has been installed, all of the Goodman control equipment is on the
car, all of the low-voltage wiring and related apparatus are installed and
functional, and the high-voltage wiring and apparatus are now being
installed. The truck-mounted air brake cylinders are being installed, and
the cabs are essentially complete. The Port's own painting department has
painted the interior ceiling, cleaned and repainted the roof, and is now
doing the prep work for repainting the carbody.
Stations- The stations at the World
Cruise Center and 6th St. are
complete except for installation of the platform bridges and signage. The
Ports O' Call Station is nearing completion of its wooden shelter. The
22nd St. Station
has its shelter completed and is awaiting installation of handrails. A
number of right-of-way improvements have also been completed, including
fencing modifications to improve sight lines. Pedestrian access
improvements are under construction adjacent to the Ports O' Call Station, and planning is
also underway for additional site improvements around all four stations.
An opening date for the line has not been set yet,
but watch this space for further bulletins as information becomes
available.
-
John
Smatlak Photos 05/22/01 -
-
click
on any image to enlarge -
|
|
|
|
|
View
from the platform at World Cruise Center station |
6th St. Station |
|
|
|
|
|
|
|
Construction
activity at
Ports
O' Call station |
Ports O' Call station |
|
|
|
|
|
|
|
22nd St. station |
Prep work begins for repainting car
1058 |
|
|
|
|
|
|
|
6/13/01
PE 1058 Update The second truck is now
installed underneath car 1058. In addition, the remainder of the
truck-mounted brake rigging is now installed, the trolley poles and other
roof apparatus are in place, and installation of the high voltage wiring
is progressing rapidly. The Port's painting department has essentially
completed the prep work for repainting the carbody, including wood repairs
to a number of the window sills. As soon as the red paint arrives,
painting will commence.
|
|
-
John
Smatlak Photos -
-
click
on any image to enlarge -
|
|
|
|
|
|
|
|
Project manager Bob Henry inspects
car 1058 |
Second truck in place under car 1058 |
|
|
|
|
|
|
|
Site work at Ports O' Call Station-
June 2001 |
F&M Locomotive personnel prepare
to mount outside-hung brake rigging on car 1058 |
|
|
|
|
7/8/01
Project Updates
1058 is now in primer coat, and the red paint will
be going on next! Since the last update, additional work has also been
completed on installation of the high voltage wiring.
Painting and roof work at the Ports O' Call Station
is nearing completion. Also, construction began in early July on the new
siding that will serve the Red Car Maintenance Building, which will be
built adjacent to the 22nd St. Station.
|
|
-
John
Smatlak Photos July 2001 -
-
click
on any image to enlarge -
|
|
|
|
|
|
|
1058
in primer coat |
Painting
in progress at Ports O' Call Station |
|
|
|
|
|
|
|
New
siding for Red Car Maintenance Building |
The
Maintenance Building will have two tracks.
22nd
St. Station is visible at right |
|
|
|
|
7/27/01
Project Updates
Car 1058 has received two coats of red
paint, and really looks spectacular! Also, since the last report, testing
has gotten started on the car's airbrake system.
Construction work continues at the
Ports O' Call station site. Painting is now completed, the light fixtures
have been installed, and work continues on the adjacent site
improvements. Work also continues at the 22nd St. Maintenance
Building site. The new siding has been ballasted and tamped, and site
preparation is underway where the building is to be built.
In other project news, the shared use
petition required by the Federal Railroad Administration for the time-separated
freight/trolley operation was formally submitted in June. This formal
submittal followed many months of consultation and dialogue with the
Pacific Harbor Line, the FRA and the California Public Utility Commission.
Working with consultant Susan Madigan of Transit Safety Management,
numerous drafts were reviewed and refined before the final submittal could
be made.
|
|
-
John
Smatlak Photos July 2001 -
-
click
on any image to enlarge -
|
|
|
|
|
|
|
|
painting
1058 |
Removing
the masking |
|
|
|
|
|
|
|
Ports
O' Call Station-July |
Work
continues at the 22nd St. Maintenance Building site |
|
|
|
|
9/7/01
Project Updates
Detail painting continues on car 1058,
including some work on the headliner area of the interior. The light
fixtures have returned from being re-plated and are being installed. Also,
initial air brake system testing has been completed, and work on the high
voltage wiring is nearing completion. Pictures of one of the cabs are
included below.
Construction of the maintenance
building has been delayed approximately three months owing to a problem with the
winning construction bid. The building is being put out for bid again the
week of September 9th. In the mean time, site preparation work has
continued; since the last update, a large surcharge of soil has been
placed in the area where the maintenance building foundation will be
located. This process is part of the required soil stabilization work at
the site.
Additional information on the replica
cars is expected shortly. Watch this space for further updates.
|
|
-
John
Smatlak Photos August 2001 -
-
click
on any image to enlarge -
|
|
|
|
|
|
|
|
1058
in fresh paint |
Soil
surcharge in place at 22nd St. Maintenance Building site |
|
|
|
|
 |
 |
|
1058
cab 9/01 |
1058
cab in progress, 7/01 |
|
|
|
|
 |
 |
|
1058
cab detail |
Goodman
controller and Wabco 26-B-1 brake valve in 1058 cab |
|
|
|
|
|
10/26/01
PE 500 replicas arrive in L.A. for completion!
The two Pacific Electric 500 Replica Cars have
arrived at the Port of Los Angeles. Completion of the cars will take place
at a Port facility over the next six to eight months. By completing the
cars in the Port, there will be an opportunity for local labor and vendors
to participate in the return of the Red Cars to Los Angeles. The public
will also be able to view the cars under construction on designated days; details
will be announced shortly.
The partly-completed cars, along with
all of the parts, arrived on Tuesday, October 16. Transportation was
provided by O.S.T. of Ventura, California. The cars are being worked on
in the same building that has housed car 1058 during its conversion back
into a railcar. The
building is located adjacent to the Port's own shop facilities, which will
permit easy utilization of the Port's wood shop, machine shop, and other
facilities.
Although the contractor in Seattle was
not able to complete the cars as originally planned, the work that was performed is of very
high quality, and will serve as an excellent foundation for completing the
cars here in Southern California.
|
|
-
John
Smatlak Photos October 2001 -
-
click
on any image to enlarge -
|
|
 |
 |
|
Car
501 arrives at the Port. The cars were covered with tarps for the trip to Southern
California. |
Car
500 arrives. Car 500 is not yet as complete as the 501. Also, most
underbody apparatus was removed from both cars to keep the height of the
load to a minimum. |
|
|
|
|
|
|
 |
 |
|
|
Car
501 was moved inside the shop using two very large forklifts. |
Car
501 heads into the shop. The other end of the building has a larger door
which will permit the two replica cars and 1058 to be rolled outside on
their trucks when they're complete. |
|
|
|
|
|
|
 |
|
|
|
Another
view of car
501 being prepared for the move into the shop. |
Some
of the many parts now on hand to complete the two cars. |
|
|
|
|
|
|
Go
to Updates Page 3 |
|
|
|
|
|
|